Stephenville Campus Construction Update

Tarleton Center First Floor “One Stop Shop”

May 28 – June 1, 2014

Ductwork has been removed that provided heating and cooling in occupied spaces on the south end of the Tarleton Center First Floor. The air handler has been shut down today. The offices affected are Residential Living and Learning, Financial Aid and Scholarships. This phase continues through Sunday. Offices will remain open.

Administration Annex II – College of Graduate Studies

May 31, 2014

The HVAC will be shut down briefly to the Administration Building for a tap into the central loop on Saturday, May 31. This shut down will begin at 7:00 a.m. and last until the completion of the project. Estimated time is two to five hours.

As always, your cooperation during these renovation phases is appreciated.

Janice Horak
Assistant Vice President – External Relations