Construction Update: Stephenville Campus

O.A. Grant Renovation Underground Power Phasing – Street Closure

  • Nancy Golden Drive will be closed from November 4 -9, 2013 due to utility installations. The area is shown in yellow in the photo at the bottom of this e-mail.
  • Sidewalks on the north end of the Administration Mall have been poured. Please be mindful of continued work in this area.

Tennis Courts

  • Fence height reduction and re-stretch has been completed. 
  • Rehabilitation of the 4 existing courts is well underway.
  • Major utility relocations are nearing completion.
  • MUSCO Lighting addition begins on November 14th with dirt work to follow immediately.
  • Once the dirt work has been completed concrete construction of the new courts will begin.

Institutional Research and Effectiveness – 2nd Floor of Tarleton Center

  • Gomez Floor Covering carpeted new office area.
  • SSC Construction has done all of the construction work.
  • Initial design concept by Aaron Wand.
  • Architect of Record – Fred B. Parker- Parker and Associates

Purchasing

  • Rehab Phase Central Receiving Phase I - complete
  • Room numbers to be installed.

McIlhaney Street Electric Rehab

  • Ongoing construction on McIlhaney Street. Please use caution in area and reduce speed. Workers, trucks, and trailers are present.

 Kiewit Building Group Photo of Underground Utility Area

Janice Horak
Assistant Vice President – External Relations